Build Update
Ora Business Park
96 Avalon Drive, Nawton, Hamilton 3200
Construction Started: 26 February 2026
Expected Completion: 1 October 2026
Progress Milestones
Resource Consent
Building Consent
Demolition, Earthworks, Foundation, Civil Works
Framing & Roofing
Cladding, Windows & Lock-Up
Internal Services
Fit-Out & Landscapping
Titles & CoC
Handover
1.Resource Consent
2.Building Consent
3.Demolition, Earthworks, Foundation, Civil Works
4.Framing & Roofing
5.Cladding, Windows & Lock-Up
6.Internal Services
7.Fit-Out & Landscapping
8.Titles & CoC
9.Handover
Work completed May 2026
- Floor slabs completed.
- Plumbing and drainage mostly completed.
- Structural steel mostly erected and wall framing installation in progress
Work Completed in April 2026
- Building pads and foundations completed.
- Plumbing and drainage in progress.
- Floor slabs underway.
Work Completed in March 2026
- Earthworks completed.
- Plumbing and drainage underway.
- Building pads constructed and foundations in progress.
Work completed in Feb 2026
- Demolition and site clearance completed
- Earthworks underway.