96 Avalon Drive, Nawton, Hamilton 3200

Construction Started: 26 February 2026

Expected Completion: 1 October 2026

Progress Milestones

1.Resource Consent

2.Building Consent

3.Demolition, Earthworks, Foundation, Civil Works

4.Framing & Roofing

5.Cladding, Windows & Lock-Up

6.Internal Services

7.Fit-Out & Landscapping

8.Titles & CoC

9.Handover


Work completed May 2026

  • Floor slabs completed.
  • Plumbing and drainage mostly completed.
  • Structural steel mostly erected and wall framing installation in progress
Photo 1
Photo 2
Photo 3
Photo 4

Work Completed in April 2026

  • Building pads and foundations completed.
  • Plumbing and drainage in progress.
  • Floor slabs underway.
Photo 1
Photo 2
Photo 3
Photo 4

Work Completed in March 2026

  • Earthworks completed.
  • Plumbing and drainage underway.
  • Building pads constructed and foundations in progress.
Photo 1
Photo 2
Photo 3
Photo 4

Work completed in Feb 2026

  • Demolition and site clearance completed
  • Earthworks underway.
Photo 1